Project Case Study
Accelerated Delivery of ABS-Certified Mud Gas Separator for Seadrill
Mud Gas Separator (MGS) for a Seadrill
Overview
Kapwell Ltd successfully engineered, fabricated, and delivered a fully ASME Section VIII and ABS MOU 2024 certified Mud Gas Separator (MGS) for a Seadrill offshore drilling application—in just 8 weeks, significantly outperforming the industry-standard delivery timeline of 25–30 weeks.
This project demonstrates Kapwell’s capability to deliver highly regulated offshore equipment under extreme schedule constraints, without compromising on quality, compliance, or performance.
Client & Application
Client: Seadrill
Rig: MOSVOLD II
Application: Offshore drilling – gas handling and well control safety
Equipment: Custom Mud Gas Separator (MGS)
The separator was designed for critical well control operations, ensuring safe handling of gas-cut drilling mud and effective gas venting during drilling activities.
Scope of Supply
Kapwell’s scope included:
- Full design, engineering, and fabrication of the MGS
- Compliance with ASME Section VIII Div. 1 pressure vessel code
- Complete ABS Drilling Rig Classification (ABS MOU 2024)
- Submission of design package including drawings, calculations, and material specifications for ABS approval
- ABS survey coordination and Certificate of Conformity (COC) issuance
- Full documentation and export-ready delivery
Technical Highlights
Process Capacity
- Mud handling: Up to 1500 GPM (≈95 m³/h)
- Gas handling: 15.3 MMSCFD
- Mud density range: 5.7–16 ppg
- Gas-liquid separation with droplet sizes of 300–450 μm
Design & Construction
- Vertical pressure vessel (2.0 m diameter, 2.864 m height)
- Material: ASTM A516 Gr. 70 (offshore grade)
- Designed for 9.5 barg pressure
- Built as per ASME VIII Div. 1 with full NDE and hydrotesting
- Internal baffle system for efficient gas-liquid separation
- ABS-compliant venting and erosion protection
Compliance & Certification
- ABS MOU 2024 Classification
- ASME pressure vessel design and fabrication
- API standards (API 53, API 12J, API 16C)
- Full inspection, testing, and documentation package
The Challenge
Mud Gas Separators with full ABS classification and ASME compliance typically require:
- Extensive design review cycles
- Third-party approvals
- Material procurement lead times
- Rigorous inspection and testing
Typical industry delivery timeline: 25–30 weeks
Kapwell’s Solution
8-Week Fast-Track Delivery
Key Execution Strategies
- Early engagement with ABS to streamline approval cycles
- Parallel engineering and procurement activities
- Immediate material sourcing and fabrication readiness
- Dedicated project management and rapid decision-making
- Optimized fabrication workflow including:
- Shell rolling & welding: 7–10 days
- NDE inspection: 7–10 days
- Hydrotesting and ABS sign-off: 3–4 days